✔️ A commitment letter stating that the work completion approval request will be submitted within a period of less than four (4) months.
✔️ An Excel file detailing the planned locations for meter installation. This will be essential to ensure consistency with the work completion approval process to be managed later. You may access the template here.
Meter cabinets must be fully ready, including:
Service entrance conductors
Branch circuits
Protective devices
Identification labels
Cabinets with no cross-connections between metered and unmetered networks (branch circuits and service entrance conductors)
You may submit your Advance Metering request by sending an email directly or through the PQR channel, following the established formats.
Please remember that, to expedite the process, it is important to complete the location format and attach the required documents mentioned above.